When the expenditure of a work exceeds or likely to exceed the amount of sanctioned estimate by more than 10%, then the prepared detailed estimate is known as:

ASupplementary estimate

BRevised estimate

CAnnual maintenance estimate

DPlinth area estimate

Answer:

B. Revised estimate