Challenger App

No.1 PSC Learning App

★
★
★
★
★
1M+ Downloads
X can complete a task in 15 days, and Y can complete the same task in 20 days. If X and Y work on alternate days starting with X, in how many days will the work be completed?

A17

B22

C15

D19

Answer:

A. 17

Read Explanation:

We are given:

  • X’s 1-day work = ( \frac{1}{15} )

  • Y’s 1-day work = ( \frac{1}{20} )

  • They work alternately starting with X

    Work in 2 days (X + Y)

115+120\frac{1}{15} + \frac{1}{20}

LCM = 60:

=460+360=760= \frac{4}{60} + \frac{3}{60} = \frac{7}{60}

So in 2 days → work done = 7/60

Find full cycles needed

We need 1 full work:

After 8 such cycles (16 days):
8×760=5660=14158 \times \frac{7}{60} = \frac{56}{60} = \frac{14}{15}

Remaining work:
1−1415=1151 - \frac{14}{15} = \frac{1}{15}

Next day is X’s turn

X does:
115\frac{1}{15}

So remaining work completes exactly in next day

Total days

  • 16 days + 1 day = 17 days

    Final Answer: 17 days


Related Questions:

രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ട് ചെയ്യും. രമ അതേ ജോലി ചെയ്യാൻ 8 ദിവസം എടുക്കും. എന്നാൽ രണ്ടുപേരും ഒരുമിച്ച് ജോലി ചെയ്താൽ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?
രാജു ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കും. ഗോപു അതേ ജോലി ചെയ്യാൻ 30 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടുപേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
ഒരാൾ 5 ദിവസംകൊണ്ട് 200 വാഴപ്പഴം കഴിച്ചു.ഓരോ ദിവസവും തലേദിവസത്തേക്കാൾ 10 എണ്ണം കൂടുതൽ കഴിച്ചുവെങ്കിൽ അയാൾ ആദ്യ ദിവസം എത്ര വാഴപ്പഴം കഴിച്ചു ?
5 പുരുഷന്മാരോ 12 സ്ത്രീകളോ അടങ്ങുന്ന ഒരു സംഘത്തിന് ഒരു പ്രത്യേക ജോലി 78 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ 5 പുരുഷന്മാരും 12 സ്ത്രീകളും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ അതേ ജോലി പൂർത്തിയാക്കാൻ എത്ര സമയം എടുക്കും ?