App Logo

No.1 PSC Learning App

1M+ Downloads
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

A$$7\frac{1}{2}$ days$

B8 days

C10 days

D7 days

Answer:

$$7\frac{1}{2}$ days$

Read Explanation:

Solution:

Given:

A can do a certain job in 12 days.

B is 60% more efficient than A.

Formula used:

work = efficiency × days

Calculation:

Let efficiency of A be 100.

The efficiency of B will be 160.

Ratio of efficiency A and B = 100 : 160 = 5 : 8

Total work = efficiency ratio of A × total days taken by A to finish work

⇒ 5 × 12 = 60 unit

Time taken by B to finish work = total work/efficiency ratio of B

608=712days\frac{60}{8}=7\frac{1}{2}days

B will finish the job in 712days7\frac{1}{2}days


Related Questions:

A,B യുടെ ഇരട്ടി വേഗത്തിൽ ജോലി ചെയ്യും. B 36 ദിവസം കൊണ്ട് ജോലി ചെയ്തു തീർക്കും എങ്കിൽ രണ്ടു പേരും കൂടി എത്ര ദിവസം കൊണ്ട് ആ ജോലി ചെയ്തു തീർക്കും?
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?
X takes twice as much time as Y or thrice as much time as Z to finish a job. Working together, the trio can finish the job in 2 days. Y alone can do the work in ______.
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?