A certain number of persons can finish a task in 85 days. If there were 15 persons more, it would have taken 25 days less for the task to be completed. How many persons are there in the beginning?

A30

B45

C40

D36

Answer:

D. 36

Read Explanation:

Solution:

Given:

Time taken to finish task = 85 days

No. of extra men added = 15

Time taken to finish the work with 15 extra men = Initial time - 25 days

= 85 - 25

= 60 days

Formula used:

M1 × D1 = M2 × D2

Calculation:

Let the initial number of men working = N

∴ N × 85 = (N + 15) × 60

⇒ 85N = 60N + 900

⇒ 25N = 900

⇒ N = 900/25

⇒ N = 36

∴ 36 men were working initially.


Related Questions:

Two pipes are connected to a water tank. The first pipe can fill the tank in 10 minutes and the second pipe can empty it in 15 minutes. If both pipes opened simultaneously, then find the time in which the tank will be completely filled with water.
60 ആളുകൾ 15 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതൽ നിയമിക്കണം ?
If John can complete a job in 8 hours and Sara can complete the same job in 12 hours how long will it take them to complete the job together ?
A and B together complete a work in 8 days. If B is 25% more efficient than A, then in how many days will A alone complete the same work?
Anil can do a piece of work in 4 hours. Ashok can do it in 8 hours. With the assistance of Robin, they completed the work in 2 hours. In how many hours can Robin alone do it?