App Logo

No.1 PSC Learning App

1M+ Downloads
C alone can complete a work in 20 days and D alone can complete the same work in 30 days. In how many days C and D together can complete the same work?

A6 days

B12 days

C15 days

D8 days

Answer:

B. 12 days

Read Explanation:

image.png

Calculation:

LCM of 20, 30 = 60

Let the total work be 60 units

⇒ Efficiency of C = 60 / 20 = 3 units / day

Efficiency of D = 60 / 30 = 2 units / day

Efficiency of C and D when working together = 3 + 2 = 5 units / day

∴ Time taken by C and D when working together = 60 / 5 = 12 days.


Related Questions:

18 പേർ 28 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 24 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ എത ജോലിക്കാർ വേണം?
Two pipes can fill a cistern separately in 10 hours and 15 hours. They can together fill the cistern in
Two pipes A and B can seperately fill a cistern in 60 min. and 75 min. respectively. There is a third pipe in the bottom of cistern to empty it. If all the three pipes are simultaneously opened, then the cistern is full in 50 min. In how much time third pipe alone can empty the cistern.
P യും Q വും ചേർന്ന് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, P ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും. Q മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ അത് ചെയ്യാൻ കഴിയും?
A, B, and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?