Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is

A36

B48

C45

D32

Answer:

B. 48

Read Explanation:

Ganesh, Ram and Sohan together can complete a work in 16 days

Ganesh and Ram together can complete the same work in 24 days,

Total work = LCM(16, 24) = 48

efficiency of Ganesh, Ram and Sohan = 48/16 = 3

Efficiency of Ganesh and Ram = 48/24 =2

Efficiency of Sohan = 3 - 2 = 1

The number of days Sohan alone takes, to finish the work = total work/ efficiency of sohan = 48/1 = 48 days


Related Questions:

A and B can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days beginning with A, then in how many days will the work be completed?
P, Q, R എന്നിവയ്ക്ക് യഥാക്രമം 8, 16, 24 ദിവസങ്ങളിൽ ഒരു ജോലി ചെയ്യാൻ കഴിയും. എല്ലാവരും ഒരുമിച്ച് ജോലി ആരംഭിച്ചു P മാത്രം ജോലി പൂർത്തിയാകുന്നത് വരെ തുടർന്നു, ആരംഭിച്ചു രണ്ടു ദിവസത്തിനുശേഷം R ഉം ജോലിപൂർത്തിയാകുന്നതിന് ഒരു ദിവസം മുൻപ് Q ഉം പിരിഞ്ഞു പോയി എങ്കിൽ ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം
8 men can complete a piece of work in 8 days while 8 women can do it in 12 days. In how many days can 2 women and 4 men complete it?
A യ്ക്ക് 10 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. B ക്ക് 15 ദിവസം കൊണ്ട് ഇതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാകും?
എ, ബി എന്നിവർ ചേർന്ന് ഒരു പണി 12 ദിവസം കൊണ്ടു വര്സിക്കുന്നു. ബി, സി 15 ദിവസവും, എ, സി 20 ദിവസവും കൊണ്ട്. എ, ബി, സി മൂന്ന് പേരും ചേർന്ന് പണി നടത്തി തികയ്ക്കാൻ എത്ര ദിവസം?