App Logo

No.1 PSC Learning App

1M+ Downloads
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

A14

B9

C6

D8

Answer:

D. 8

Read Explanation:

Solution:

Given:

Number of man days required to complete the work = 56

Calculation:

Let the number of man be "m" and number of days be "d"

Number of man days = m × d = 56

Number of man = (m – 1)

⇒ Number of days = (d + 1)

⇒ Number of man days = (m – 1) (d + 1)

⇒ md =(m – 1) (d + 1)

⇒ md = md – d + m – 1

⇒ m – d = 1

putting d = 56/m 

⇒ m – 56/m = 1 

⇒ m2 – 56 = m

⇒ m2 – m – 56 = 0

⇒ m2 – 8m + 7m – 56 = 0

⇒ m(m – 8) + 7(m – 8) = 0

⇒ (m – 8) (m + 7) = 0 

⇒ m = 8, – 7 

m is number of man, so m cannot be negative 

⇒ m = 8 

∴ The Number of workers is 8.


Related Questions:

A can do a work in 12 days, B can do it in 20 days and C in 15 days. If they work together the number of days needed to complete the work is:
15 ജോലിക്കാർ 4 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്തു തീർക്കുന്നു. അതേ ജോലി ചെയ്യാൻ 5 പേരുണ്ടെങ്കിൽ എത്ര ദിവസം വേണം ?
A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
A and B together can complete a work in 8 days. B alone can complete the work in 24 days. In how many days A alone can complete the same work?
Two pipes X and Y can fill a cistern in 21 hours and 24 hours, respectively. The pipes are opened simultaneously and it is found that due to a leakage in the bottom it takes 48 minutes more to fill the cistern. When the cistern is full, in how much time will the leak empty it if no pipe is open during that time?