App Logo

No.1 PSC Learning App

1M+ Downloads
If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

A96 days

B128 days

C64 days

D118 days

Answer:

B. 128 days

Read Explanation:

Solution: Given: Rohit alone can complete one-fourth of a work in 32 days Formula used: (M × D × H/W = constant Where, M = number of person D = number of days H = number of hours W = work done Also, Work is directly proportional to days Calculation: One-fourth of the work can be completed in 32 days Then, Complete work will be completed in 32 × 4 = 128 days


Related Questions:

A pipe can fill a tank in 6 hours, and another pipe can fill the same tank in 8 hours. If both pipes are opened at the same time, how long (in hours, rounded off to one decimal place) will it take to fill the tank?
The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days and then Raja and Mohan work for next 4 days and the remaining work is completed by Mohan. Find the total time taken to complete the work.
9 കുട്ടികൾക്ക് 360 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. 18 പുരുഷന്മാർക്ക് ഇതേ ജോലി 72 ദിവസം കൊണ്ടും 12 സ്ത്രീകൾക്ക് 162 ദിവസം കൊണ്ടും പൂർത്തിയാക്കാനാകും. 4 പുരുഷന്മാരും 12 സ്ത്രീകളും 10 കുട്ടികളും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
ഒരാൾ ഒരു ദിവസം കൊണ്ട് 2 മീറ്റർ × 2 മീറ്റർ × 2 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കും. ഇതേ നിരക്കിൽ 3 പേർ ചേർന്ന് 4 മീറ്റർ × 4 മീറ്റർ × 4 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?
A Pipe can fill a tank in 10 hours. Due to leak in the bottom it fills the tank in 30 hours. If the tank is full, how much time will the leak take to empty it