P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?

A8 days

B4 days

C6 days

D10 days

Answer:

B. 4 days

Read Explanation:

1. Find P's work rate:

  • Since P works twice as fast as Q, P can complete the same work in half the time.

  • P alone can complete the work in 12 days / 2 = 6 days.

2. Calculate individual work rates:

  • Q's work rate: Q completes 1/12 of the work per day.

  • P's work rate: P completes 1/6 of the work per day.

3. Calculate combined work rate:

  • Combined work rate = P's work rate + Q's work rate

  • Combined work rate = (1/6) + (1/12) = 3/12 = 1/4

4. Find the time taken together:

  • Time taken to complete the work together = 1 / Combined work rate

  • Time taken = 1 / (1/4) = 4 days

Therefore, working together, P and Q will take 4 days to complete the work.


Related Questions:

If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?
Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
Isha can do a certain piece of work in 15 days. Isha and Smriti can together do the same work in 11 days, and Isha, Smriti and Ashlesha can do the same work together in 10days. In how many days can Isha and Ashlesha do the same work?
8 men can complete a piece of work in 8 days while 8 women can do it in 12 days. In how many days can 2 women and 4 men complete it?
40 mechanics can repair a bike in 56 days. In how many days 32 mechanics will do the same work?