App Logo

No.1 PSC Learning App

1M+ Downloads
Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?

A32 days

B40 days

C45 days

D60 days

Answer:

B. 40 days

Read Explanation:

P alone can do it in 10 days , $Efficiency of P =\frac{1}{10}$

Q alone can do it in 24 days,

EfficiencyofQ=124Efficiency of Q =\frac{1}{24}

Together they can do it in 6days

$Efficiency of Q=\frac{1}{6}$

$\frac1{10}+\frac{1}{24}+\frac{1}{R}=\frac{1}{6}$

$\frac1{R}=\frac{1}{40}$

$R=40 Days$

Alternate method

image.png

EffrciciencyofP+Q+R=20Effrciciency of P+Q+R=20

R=20(12+5)R=20-(12+5)

EfficiencyofR=3Efficiency of R=3

$$Time taken by R alone to complete a work is$=\frac{120}{3} = 40 days$


Related Questions:

Two pipes A and B can fill a tank in 15 and 30 minutes respectively. If both the pipes are used together, then how long will it take to fill the tank ?
K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ടും രാജു അതേ ജോലി 18 ദിവസം കൊണ്ടും ചെയ്യും. രണ്ടുപേരുംചേർന്നു ജോലി ചെയ്താൽ മുഴുമിക്കാൻ എത്ര ദിവസം വേണം?
A യും B യും ചേർന്ന് 30 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ആരംഭിച്ചെങ്കിലും 6 ദിവസത്തിന് ശേഷം A ജോലി ഉപേക്ഷിച്ചു, 36 ദിവസങ്ങൾ കൂടി കഴിഞ്ഞ് B ജോലി പൂർത്തിയാക്കുന്നുവെങ്കിൽ, A എത്ര ദിവസം കൊണ്ട് അതേ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
A and B together can finish a work in 16 days, while B can do the same work alone in 24 days. In how many days can A alone finish the work ?