App Logo

No.1 PSC Learning App

1M+ Downloads
X and Y can complete a piece of work in 8 days and 12 days, repectively. If they work on alternate days, with X working on the first day , how long will it take the duo to complete the same work?

A925days9\frac{2}{5}days

B935days9\frac{3}{5}days

C923days9\frac{2}{3}days

D912days9\frac{1}{2}days

Answer:

912days9\frac{1}{2}days

Read Explanation:

X can do the work in 8 days

Y can do the work in 12 days

LCM of 8 , 12 is 24

Total work =24

.Efiiciency of X = 248=3\frac{24}{8}=3

Efficiency of Y = 2412=2\frac{24}{12}=2

Working on alternate days start with X

3+2 = 5 work done on 2days

in 4days 10 work done

in 6 days 15 work done

in 8days 20 work done

in 9days 23 work done

Remaining 1 work done by Y

9+12=912days9+\frac{1}{2}=9\frac{1}{2}days


Related Questions:

Six typists can type a given data in 16 days. How many days will 4 typists take to do the same work?
2 പേർ, 20 ദിവസം കൊണ്ട് 10 അടി ഉയരമുള്ള ഒരു മതിൽ കെട്ടും. എങ്കിൽ അതേ മതിൽ കെട്ടാൻ 5 ആളുകൾ എത്ര ദിവസങ്ങളെടുക്കും ?
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 12 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is:
Two pipes A and B can seperately fill a cistern in 60 min. and 75 min. respectively. There is a third pipe in the bottom of cistern to empty it. If all the three pipes are simultaneously opened, then the cistern is full in 50 min. In how much time third pipe alone can empty the cistern.