Chutak Hydro - electric project being constructed by NHPC in Kargil is on the river -

ASuru

BJhelum

CKunar

DRavi

Answer:

A. Suru

Read Explanation:

The Chutak Hydroelectric Plant is a run-of-the-river power project on the Suru River (a tributary of Indus) in Kargil district in the Indian union territory of Ladakh (231 km (144 mi) from the capital Leh). The barrage of the project is at Sarze village and the powerhouse is located on the right bank of the Suru near Chutak village. The project construction began on 23 September 2006, and the first three generators were commissioned in November 2012. The fourth was commissioned in January 2013.


Related Questions:

താഴെ തന്നിരിക്കുന്നവയിൽ ഏറ്റവും കൂടുതൽ മലിനീകരിക്കപ്പെട്ട നദി ഏത് ?
ഗോമതിയുടെ നീളം എത്ര ?
വിന്ധ്യാ - സത്‌പുര പർവ്വത നിരകൾക്കിടയിലൂടെ ഒഴുകുന്ന നദി ഏതാണ് ?
Which river is associated with the Narmada Bachao Andolan and the Sardar Sarovar Project?
The river that emerges from the mountains at Attock and flows southward into the plains of Pakistan is: