App Logo

No.1 PSC Learning App

1M+ Downloads
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many days will the work be completed?

A47.5

B49.5

C42.5

D45.5

Answer:

A. 47.5

Read Explanation:

Total workload = 60 × 40 = 2400 60 men did the work in 10 days = 600 55 men did the work in 10 days = 550 50 men did the work in 10 days = 500 45 men did the work in 10 days = 450 Total work units left = 2400 – (600 + 550 + 500 + 450) = 2400 – 2100 = 300 40 men will do 300 units in = 300/40 = 7.5 Total number of days to finish the work = 40 + 7.5 = 47.5 days


Related Questions:

32 പേർ 6 മണിക്കൂർ വീതം ജോലി ചെയ്താൽ 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കുന്ന ഒരു ജോലി 24 പേർ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ ഒരു ദിവസം എത്ര മണിക്കൂർ ജോലി ചെയ്യണം?
A, B and C together can build a wall in 12 days. C is four times as productive as B and A alone can build the wall in 48 days. In how many days A and B working together can build the wall?
6/7 part of a tank is filled with oil. After taking out 60 litres of oil the tank is 4/5 part full. What is the capacity (in litres) of the tank?
If two pipes can fill a tank in 20 minutes & 30 minutes respectively. If both the pipes are opened simultaneously, then the tank will be filled in
If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?