Challenger App

No.1 PSC Learning App

1M+ Downloads
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?

A8

B10

C7

D9

Answer:

B. 10

Read Explanation:

8 men = 10 women ie, 5 women = 4 men 28 men + 15 women = 28 men + 12men = 40 men 8 men can do a piece of work in 50 days 1 men can do the same work in (50 × 8) days Then 40 men can do the same work in (50 × 8)/40 = 10 days


Related Questions:

A 60 ദിവസം കൊണ്ടും B 40 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യുമെങ്കിൽ രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി ചെയ്യും?
A and B together can complete a work in 8 days. B alone can complete the work in 24 days. In how many days A alone can complete the same work?
Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes are opened simultaneously, after how much time should A be closed so that the tank is full in 20 minutes?
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Jitesh and Kamal can complete a certain piece of work in 18 and 17 days, respectively, They started to work together, and after 5 days, Kamal left. In how many days will Jitesh complete the remaining work?