Challenger App

No.1 PSC Learning App

1M+ Downloads
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?

A8

B10

C7

D9

Answer:

B. 10

Read Explanation:

8 men = 10 women ie, 5 women = 4 men 28 men + 15 women = 28 men + 12men = 40 men 8 men can do a piece of work in 50 days 1 men can do the same work in (50 × 8) days Then 40 men can do the same work in (50 × 8)/40 = 10 days


Related Questions:

രേഖയ്ക്കും സൊണാലിക്കും 20 ദിവസത്തെ കൂലിയായി ലഭിച്ചത് 2800 രൂപയാണ്. സൊണാലിയുടെ മൂന്നിരട്ടിയായിരുന്നു രേഖയുടെ ജോലിയിലെ കാര്യക്ഷമത. സൊണാലിയുടെ ദിവസ വേതനം എത്രയാണ്?

A can complete 331333\frac{1}{3} % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

Jitesh and Kamal can complete a certain piece of work in 7 and 16 days, respectively, They started to work together, and after 2 days, Kamal left. In how many days will Jitesh complete the remaining work?
8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?
There are two pipes leading to a tank. If pipe A alone is opened, the tank will be filled in 1 hour. If pipe B alone is opened, the tank will be filled in 1 hour 30 minute Both pipes were opened together. After 27 minute pipe B was closed. How long could pipe A left open to fill the rest of the tank?