App Logo

No.1 PSC Learning App

1M+ Downloads

8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?

A8

B10

C7

D9

Answer:

B. 10

Read Explanation:

8 men = 10 women ie, 5 women = 4 men 28 men + 15 women = 28 men + 12men = 40 men 8 men can do a piece of work in 50 days 1 men can do the same work in (50 × 8) days Then 40 men can do the same work in (50 × 8)/40 = 10 days


Related Questions:

Three pipes A, B, C can empty a tank in 10 hours, 15 hours, 30 hours respectively. If all the three pipes are open simultaneously how much time will the tank be empty.

A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.

54kg ധാന്യം 35 കുതിരകൾക്ക് 21 ദിവസത്തേക്ക് തികയുമെങ്കിൽ 72kg ധാന്യം 28 കുതിരകൾക്ക് എത്ര ദിവസത്തേക്ക് തികയും?

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days how long will B alone take to complete the job ?

ഒരാൾ ഒരു ദിവസം കൊണ്ട് 2 മീറ്റർ × 2 മീറ്റർ × 2 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കും. ഇതേ നിരക്കിൽ 3 പേർ ചേർന്ന് 4 മീറ്റർ × 4 മീറ്റർ × 4 മീറ്റർ സൈസിൽ ഒരു കുഴി നിർമ്മിക്കാൻ എത്ര ദിവസം വേണം?