App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?
അരുണിന് 80 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും . അവൻ 10 ദിവസം അതിൽ ജോലി ചെയ്യുന്നു തുടർന്ന് ബാക്കിയുള്ള ജോലി അനിൽ മാത്രം 42 ദിവസം കൊണ്ട് പൂർത്തിയാക്കുന്നു . അരുണും അനിലും ചേർന്ന് ജോലി ചെയ്താൽ എത്ര സമയത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കും ?
18 ജോലിക്കാർ 5 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 6 ദിവസം കൊണ്ടു ചെയ്തു തീർക്കാൻ എത്ര പേർ വേണം?
ഒരു പ്രത്യേക ജോലി 10 പുരുഷന്മാർക്കോ 15 സ്ത്രീകൾക്കോ 24 ദിവസത്തിനുള്ളിൽ പൂർത്തിയാക്കാൻ കഴിയും 4 പുരുഷന്മാരും 9 സ്ത്രീകളും അടങ്ങുന്ന ഒരു ടീമിന് അതേ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ ആകും?
Ravi, Rohan and Rajesh alone can complete a work in 10, 12 and 15 days respectively. In how many days can the work be completed, if all three work together?