Ravi, Rohan and Rajesh alone can complete a work in 10, 12 and 15 days respectively. In how many days can the work be completed, if all three work together?

A4 days

B5 days

C3 days

D8 days

Answer:

A. 4 days

Read Explanation:

Ravi can complete a work in = 10 days

∴ In 1 day Ravi can do = 110\frac{1}{10}

Rohan alone can complete a work in = 12 days

∴ In 1 day Rohan can do = 112\frac{1}{12}

Rajesh alone can complete a work in = 15 days

∴ In 1 day Rajesh can do = 115\frac{1}{15}

∴ In 1 day they together can do = 110+112+115\frac{1}{10} + \frac{1}{12} + \frac{1}{15} = (6+5+4)60=14\frac{(6 + 5 + 4)}{60} =\frac{1}{4}

∴ They together can complete the work in = 4 days


Related Questions:

Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?
A, B and C contract to do a work for Rs. 4200. A can do the work in 6 days, B in 10 days and C in 12 days. If they work together to do the work, what is the share of C (in Rs.)?
Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.
Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?