App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?

ARs. 400

BRs. 500

CRs. 600

DRs. 200

Answer:

B. Rs. 500

Read Explanation:

Total work = LCM of 10, 15 = 30 Efficiency of A = Total work / Time taken = 30 / 10 = 3 Efficiency of B = Total work / Time taken = 30 / 15 = 2 The efficiency of both = Efficiency of A + Efficiency of B = 3 + 2 = 5 Amount per day = Total amount / Efficiency of both = 1250 / 5 = Rs. 250 The amount B get = Amount per day x Efficiency of B = 250 x 2 = Rs. 500


Related Questions:

Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24 days joined them after 4 days. Under the circumstances in how many days the work will be completed?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A ഒരു ജോലി 16 ദിവസവും B 12 ദിവസവും ചെയ്യുന്നു. B യും ഒരു ആൺകുട്ടിയും ജോലി 8 ദിവസത്തിനുള്ളിൽ പൂർത്തിയാക്കും. ആൺകുട്ടി മാത്രം ജോലി ചെയ്യാൻ എത്ര സമയമെടുക്കും?
48 ആളുകൾ 14 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി 12 ദിവസം കൊണ്ട് തീർക്കണമെങ്കിൽ എത്ര പേരെ കൂടുതലായി നിയമിക്കണം?
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many days will the work be completed?