App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 60% of the job?

A18

B30

C25

D24

Answer:

A. 18

Read Explanation:

Solution: Given: A can do a job in 10 days B can do a job in 5 days Formula used: Efficiency = Total work/Time taken Calculation: LCM of 10 and 5 = 10 = Total work Efficiency of A = 10/10 = 1 unit/day Efficiency of B = 10/5 = 2 units/day A and B work for 2 days ⇒ (1 + 2) × 2 units ⇒ 6 units Remaining work = (10 – 6) units ⇒ 4 units A and C can complete the remaining work in 3 days A and C one day work ⇒ 4/3 C one day work ⇒ (4/3) – 1 ⇒ 1/3 C can complete 60% of work in ⇒ 6 ÷ (1/3) ⇒ 18 days ∴ C can complete 60% of work in 18 days.


Related Questions:

Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?
A job is completed by 10 men in 20 days and by 20 women in 15 days. How many days will it take for 5 men and 10 women to finish that work ?
Three pipes A, B, C can empty a tank in 10 hours, 15 hours, 30 hours respectively. If all the three pipes are open simultaneously how much time will the tank be empty.
A,B,C എന്നീ മൂന്ന് പൈപ്പുകൾക്ക് യഥാക്രമം 10, 15, 30 മണിക്കൂർ കൊണ്ട് ഒരു വാട്ടർ ടാങ്ക് ശൂന്യമാക്കാൻ കഴിയും. മൂന്ന് പൈപ്പുകളും ഒരേസമയം തുറന്നാൽ, ടാങ്ക് ശൂന്യമാക്കാൻ എത്ര സമയം (മണിക്കൂറുകൾ) എടുക്കും?
A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.