A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.

A33

B18

C36

D25

Answer:

C. 36

Read Explanation:

let the original number of workers be x then x * 22 = (x-3) * 24 22x = 24x -72 24x - 22x = 72 2x = 72, x=36 No of original workers = 36


Related Questions:

A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450 eggs?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
12 men and 16 women can complete a job in 5 days. 13 men and 24 women can complete the same job in 4 days. How long in days, will 5 men and 10 women take to complete the same job?
A and B can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days beginning with A, then in how many days will the work be completed?