A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.

A33

B18

C36

D25

Answer:

C. 36

Read Explanation:

let the original number of workers be x then x * 22 = (x-3) * 24 22x = 24x -72 24x - 22x = 72 2x = 72, x=36 No of original workers = 36


Related Questions:

After 60 litres of petrol was poured into an empty storage tank, it was still 10% empty. How much petrol (in litres, rounded off to two decimal place) must be poured into the storage tank in order to fill it?
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?
Jitesh and Kamal can complete a certain piece of work in 18 and 17 days, respectively, They started to work together, and after 5 days, Kamal left. In how many days will Jitesh complete the remaining work?
Alice can do a piece of work in 10 days Anu can do the same work in 12 days and Meera do the work in 15 days. If they work together low long will they take to complete the work?
Abhinav, Bikash and Chetan can complete a piece of work in 16 days, 24 days and 32 days respectively. If Bikash leaves 2 days before completion of the work, then find the total days required to complete the work.