App Logo

No.1 PSC Learning App

1M+ Downloads
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?

A4 days

B6 days

C8 days

D10 days

Answer:

B. 6 days

Read Explanation:

Let, B alone can complete the work in be x days

According to the question,

112+1x=14\frac{1}{12}+\frac{1}{x} = \frac{1}{4}

1x=14112\frac{1}{x} =\frac{1}{4}-\frac{1}{12}

1x=(31)12\frac{1}{x} = \frac{(3-1)}{12}

1x=16\frac{1}{x} =\frac{1}{6}

⇒ x = 6

∴ B alone can complete the work in 6 days

Alternate Solution

Let total work done be 12 units (LCM of 4 and 12)

Hence,

Efficiency of A + B = 124=3units/day\frac{12}{4} = 3 units/day

Efficiency of A = 1212=1unit/day\frac{12}{12} = 1 unit/day

Now, efficiency of B = 3 - 1 = 2 units/day

∴ Required days = Total work/Efficiency of B = 122=6days\frac{12}{2} = 6 days


Related Questions:

A 60 ദിവസം കൊണ്ടും B 40 ദിവസം കൊണ്ടും ഒരു ജോലി ചെയ്യുമെങ്കിൽ രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ഈ ജോലി ചെയ്യും?
K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?
A pipe can fill the tank in 10 minutes and another pipe can empty it in 12 minutes. If both the pipes are opened the time in which the tank is filled
8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?