App Logo

No.1 PSC Learning App

1M+ Downloads
A and B undertake to complete a piece of work for ₹600. A alone can complete it in 4 days while B alone can complete it in 6 days. With the help of C, they finish the work in 2 days. Find the share of C in the payment received.

A200

B78

C100

D300

Answer:

C. 100

Read Explanation:

A alone complete a work =4 days B alone complete a work =6 days LCM of these two is the work ie =12 efficiency of A=12/4=3 efficiency of B = 12/6=2 A and B are work together the one day work is 5 if C is included the work they will complete the work in 2 days so the efficiency of C is 2 days=12/efficiency of (A+B+C) 2=12/(5+C) 1=6/(5+C) (5+C)=6 C=1 so the ratio of efficiency of A:B:C = 3:2:1 the share of C=600*(1/6)=100


Related Questions:

Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
Kiran can do a certain piece of work in 15 days. Kiran and Garima can together do the same work in 10 days, and Kiran, Garima and Mehak can do the same work together in 9 days. In how many days can Kiran and Mehak do the same work?
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?
A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:
A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, A യ്ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് അതേ ജോലി ചെയ്യാൻ കഴിയും. B-ക്ക് മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ ഒരേ ജോലി ചെയ്യാൻ കഴിയും?