App Logo

No.1 PSC Learning App

1M+ Downloads
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.

A29 days

B25 days

C15 days

D24 days

Answer:

B. 25 days

Read Explanation:

Solution: Given data: Time taken by A to complete the work = 42 days Time taken by B to complete the work = 56 days Time taken by C to complete the work = 63 days A left the work 10 days before completion B left the work 12 days before completion The concept: LCM (Least Common Multiple) and work done concept Find LCM of 42, 56, and 63 to find the total units of work. Use work = efficiency × time to find the work done by each individual. Calculation: LCM of 42, 56, 63 = 504 units ⇒ Daily work done by A = 504 / 42 = 12 units/day ⇒ Daily work done by B = 504 / 56 = 9 units/day ⇒ Daily work done by C = 504 / 63 = 8 units/day Let's assume the work is completed in D days. ⇒ Total work done by A = 12 × (D - 10) (as A left 10 days before completion) ⇒ Total work done by B = 9 × (D - 12) (as B left 12 days before completion) ⇒ Total work done by C = 8 × D Summing up work done by A, B, and C should be equal to total units of work (504). ⇒ 12(D - 10) + 9(D - 12) + 8D = 504 ⇒ 12D - 120 + 9D - 108 + 8D = 504 ⇒ (12 + 9 + 8)D = 504 + 120 + 108 ⇒ 29D = 732 ⇒ D = 732 / 29 ⇒ D ≈ 25 days Therefore, the work will be completed in approximately 25 days.


Related Questions:

Pipes A and B can empty a full tank in 5 hours and 12 hours respectively. Pipe C can fill the same empty tank in 2 hours. If all the three pipes are opened together, then the tank will be filled in:
If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?

A can complete 331333\frac{1}{3} % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

32 പേർ 6 മണിക്കൂർ വീതം ജോലി ചെയ്താൽ 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കുന്ന ഒരു ജോലി 24 പേർ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ ഒരു ദിവസം എത്ര മണിക്കൂർ ജോലി ചെയ്യണം?
The working efficiency of Ram, Shyam and Shiva is 4 : 2 : 1. Shiva alone can complete the work in 100 days. If Ram and Shyam work together for 16 days and leave, then find the number of days required by Shiva to complete the remaining work.