Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.

A8 days

B7 2/3 days

C7 days

D6 days

Answer:

A. 8 days

Read Explanation:

Let the required days be x A work for (x-2) days, while 'B' work for 'x' days According to the question, (x - 2)/10 + x/20 = 1 2x - 4 +x = 20 3x =24 x = 8 days


Related Questions:

A pipe can fill a tank with water in 3 hours. Due to leakage in bottom, it takes 3 ½ hours to fill it. In what time the leak will empty the fully filled tank ?
Two pipes A and B can fill a tank in 6 hours and 8 hours respectivley. If both the pipes are opened together, then after how many hours should B be closed so that the tank is full in 4 hours ?

A can do 15\frac{1}{5}th of a work in 4 days and B can do 16\frac{1}{6}th of the same work in 5 days. In how many days they can finish the work, if they work together?

3 പുരുഷന്മാർക്കും 4 കുട്ടികൾക്കും 7 ദിവസത്തിനുള്ളിൽ 756 രൂപ സമ്പാദിക്കാം, 11 പുരുഷന്മാർക്കും 13 കുട്ടികൾക്കും 8 ദിവസത്തിനുള്ളിൽ 3008 രൂപ സമ്പാദിക്കാൻ കഴിയും, എത്ര ദിവസത്തിനുള്ളിൽ 7 പുരുഷന്മാർക്കും 9 കുട്ടികൾക്കും 2480 രൂപ സമ്പാദിക്കാൻ കഴിയും?
ഒരു പരീക്ഷ തുടങ്ങാനായി ഒരു ബെല്ലടിക്കുകയും തുടർന്ന് ഓരോ അരമണിക്കൂർ കഴിയുമ്പോഴും ഓരോ ബെല്ലടിക്കുകയും ചെയ്യുന്നു. ആകെ 6 ബെല്ലടിച്ചുവെങ്കിൽ പരീക്ഷ സമയം എത്ര ?