Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.

A8 days

B7 2/3 days

C7 days

D6 days

Answer:

A. 8 days

Read Explanation:

Let the required days be x A work for (x-2) days, while 'B' work for 'x' days According to the question, (x - 2)/10 + x/20 = 1 2x - 4 +x = 20 3x =24 x = 8 days


Related Questions:

Sankar and Vishnu work alternately in a tailoring shop on an order of stitching 21 suits. Sankar starts the work, stitches 3 suits in two days, and takes a break, during which Vishnu stitches 3 suits in three days, and then takes a break. This pattern is repeated till all the 21 suits are stitched. How many days did it take the duo to complete the work?
36 ആളുകൾ 25 ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 15 ആളുകൾ എത്ര ദിവസം കൊണ്ട് തീർക്കും?
A എന്ന് പൈപ്പ് തുറന്നാൽ ടാങ്ക് നിറയാൻ 10 മിനിറ്റ് വേണം. B എന്ന പൈപ്പ് തുറന്നാൽ നിറഞ്ഞിരിക്കുന്ന ടാങ്ക് 15 മിനിറ്റ് കൊണ്ട് കാലിയാകും. എന്നാൽ രണ്ട് പൈപ്പും ഒരുമിച്ചു തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?
രാജിന് മാത്രം 8 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും. രാമന് മാത്രം 12 ദിവസം കൊണ്ട് ഇത് ചെയ്യാൻ കഴിയും. ജോലിയുടെ മൊത്തം വേതനം 500 രൂപയാണെങ്കിൽ. ജോലിയുടെ മുഴുവൻ കാലയളവിലും അവർ ഒരുമിച്ച് ജോലി ചെയ്യുകയാണെങ്കിൽ രാജിന് എത്ര ശമ്പളം നൽകണം?
20 പേർ ഒരു ജോലി 5 ദിവസം കൊണ്ട് തീർക്കുന്നു. ആ ജോലി ഒരു ദിവസം കൊണ്ട് തീർക്കാൻ എത്രപേർ വേണം?