Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.

A8 days

B7 2/3 days

C7 days

D6 days

Answer:

A. 8 days

Read Explanation:

Let the required days be x A work for (x-2) days, while 'B' work for 'x' days According to the question, (x - 2)/10 + x/20 = 1 2x - 4 +x = 20 3x =24 x = 8 days


Related Questions:

A can do a piece of work in 15 days. B is 25% more efficient than A and C is 40% more efficient than B. A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:
A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:
എ, ബി എന്നീ രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 20, 30 മിനിറ്റുകൾ കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും ഒരുമിച്ച് ഉപയോഗിച്ചാൽ, ടാങ്ക് നിറയാൻ എത്ര സമയമെടുക്കും?
Working alone, A can do a job in 15 days and B can do the same job in 18 days. In how many days will the job be completed if both work together?
ഒരു വാഹനം യാത്രയുടെ ആദ്യത്തെ 120 കി.മീറ്റർ ദൂരം ശരാശരി 30 കിമീ/മണിക്കൂർ വേഗത്തിലും അടുത്ത 120 കീ മീറ്റർ 20 കിമീ/മണിക്കൂർ വേഗത്തിലുമാണ് സഞ്ചരിച്ചത് . എന്നാൽ മുഴുവൻ യാത്രയിലെയും ശരാശരി വേഗം എത്രയാണ് ?