Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in.

A8 days

B7 2/3 days

C7 days

D6 days

Answer:

A. 8 days

Read Explanation:

Let the required days be x A work for (x-2) days, while 'B' work for 'x' days According to the question, (x - 2)/10 + x/20 = 1 2x - 4 +x = 20 3x =24 x = 8 days


Related Questions:

A, B and C can do a work in 20, 30 and 60 days respectively. If total Rs, 3000 is given to them, then find their individual share.
In a computer game, a builder can build a wall in 20 hours while a destroyer can completely demolish such a wall in 40 hours. In the beginning, both builder and destroyer were set to work together on a basic level. But after 30 hours the destroyer was withdrawn. What was the total time taken to build the wall?
ഒരു പ്രത്യേക ജോലി 10 പുരുഷന്മാർക്കോ 15 സ്ത്രീകൾക്കോ 24 ദിവസത്തിനുള്ളിൽ പൂർത്തിയാക്കാൻ കഴിയും 4 പുരുഷന്മാരും 9 സ്ത്രീകളും അടങ്ങുന്ന ഒരു ടീമിന് അതേ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ ആകും?
Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
20 ആളുകൾ 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ജോലി ചെയ്യാൻ 5 പേർക്ക് എത്ര ദിവസം വേണം ?