A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?

A6 days

B12 days

C4days

D8 days

Answer:

A. 6 days

Read Explanation:

work done by A for 3 days = 3/12=1/4 Remaining work = 1 - 1/4 = 3/4 work done by (A+B) for 1 day=(3/4)*(1/3)=1/4 work done by B for 1 day=(1/4)-(1/12)=2/12=1/6. B alone will complete the work in 6 days


Related Questions:

Raj alone can do a piece of work in 8 days. Raman alone can do it in 12 days. If the total wage for the work is Rs. 500. How much should Raj be paid if they work together for the entire duration of the work?
A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?
ഒരു ടയറിന് രണ്ട് പഞ്ചറുകളുണ്ട്. ആദ്യ പഞ്ചർ മാത്രം 10 മിനിറ്റിനുള്ളിൽ ടയറിനെ ഫ്ലാറ്റ്ആക്കും, രണ്ടാമത്തേത് മാത്രം 8 മിനിറ്റിനുള്ളിൽ ഇത് ചെയ്യുമായിരുന്നു. വായു ഒരു കോൺസ്റ്റൻറ്നിരക്കിൽ പുറത്തേക്ക് ഒഴുകുകയാണെങ്കിൽ, അത് ഫ്ലാറ്റ് ആക്കാൻ രണ്ട് പഞ്ചറുകളും ഒരുമിച്ച് എത്രസമയം എടുക്കും?
A pipe can filla tankin 30 minutes. Due to a leak in the bottom it is filled in 40 minutes. If the tank is full, how much time will the leak take to empty it?
ശശിയും സോമനും കൂടി ഒരു ജോലി 12 ദിവസം കൊണ്ട് തീർക്കും. ശശിക്ക് ഒറ്റയ്ക്ക് ആ ജോലി തീർക്കാൻ 20 ദിവസം വേണമെങ്കിൽ സോമന് ആ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം?