Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?

A12

B10

C9

D6

Answer:

A. 12

Read Explanation:

total work = LCM(10,15) = 30 work done by A in one day = 1/10 work done by A in one day = 1/15 work done by A + B in 2 days = 1/10 + 1/15 = 1/6 work done by A + B in one day = 1/12 Time taken by A and B to complete the work = 12 days


Related Questions:

If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

A can complete 331333\frac{1}{3} % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

If 10 men and 12 women can earn Rs.12880 in 7 days, and 15 men and 6 women can earn Rs.17280 in 9 days, then in how many days will 8 men and 10 women earn Rs.15000?