A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?

A12

B10

C9

D6

Answer:

A. 12

Read Explanation:

total work = LCM(10,15) = 30 work done by A in one day = 1/10 work done by A in one day = 1/15 work done by A + B in 2 days = 1/10 + 1/15 = 1/6 work done by A + B in one day = 1/12 Time taken by A and B to complete the work = 12 days


Related Questions:

A can make a divider in 20 days, while B can make it in 50 days. If they work together and get Rs.3500, then find the share of B in the amount.
പൈപ്പ് X, Z എന്നിവയ്ക്ക് 18 മണിക്കൂറും 4 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാൻ കഴിയും. പൈപ്പ് X 9:00 a.m നും പൈപ്പ് Z 4:00 p.m നും തുറന്നാൽ, ഏത് സമയത്താണ് ടാങ്ക് നിറയുക?
Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?
A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, A യ്ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് അതേ ജോലി ചെയ്യാൻ കഴിയും. B-ക്ക് മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ ഒരേ ജോലി ചെയ്യാൻ കഴിയും?