How many men will be required to plough 50 acres of land in 10 days if 15 men are required 6 days to plough 10 acres of land?

A45

B40

C55

D50

Answer:

A. 45

Read Explanation:

Solution: Given: 15 men required 6 days to plough 10 acres of land Formula Used: M­1D1/W1 = M­2D2/W2 Calculation: ⇒ M­1 = 15, D1 = 6, W1 = 10 ⇒ M­2 =? ,D2 = 10, W2= 50 ⇒ 15 × 6/10 = M2 × 10/50 ⇒ M2 = 45 ∴ The total men required is 45


Related Questions:

12 ആളുകൾ 25 ദിവസംകൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 15 ദിവസംകൊണ്ട് തീർക്കാൻ ഇനി എത ആളുകൾ കൂടി വേണം?
8 men and 12 women finish a job in 4 days. While 6 men and 14 women in 5 days. In how many days will 20 women finish the job?
Ravi, Rohan and Rajesh alone can complete a work in 10, 12 and 15 days respectively. In how many days can the work be completed, if all three work together?
The working efficiency of Raja, Ram and Mohan is 6 : 3 : 2. Raja can complete the whole work in 10 days. Raja and Ram together work for the first two days and then Raja and Mohan work for next 4 days and the remaining work is completed by Mohan. Find the total time taken to complete the work.
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?