App Logo

No.1 PSC Learning App

1M+ Downloads
If 16 men or 28 women can do a work in 40 days. How long 24 men and 14 women will take to complete the work ?

A15 days

B18 days

C20 days

D22 days

Answer:

C. 20 days

Read Explanation:

16 men = 28 women 8 men = 14 women 24 men + 14 women = 24 men + 8 men = 32 men 16 men can do a piece of work in 40 days 1 men can do the same work in (40 × 16) days Then 32 men can do the same work in (40 × 16)/32 = 20 days


Related Questions:

30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തുതീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A & B together do a work in 40 days. B & C together do in 25 days. A and B started working together, and A left work after 6 days & B left work after 8 days. After A left, C join the work & C completed the work in 40.5 days, C alone can complete the work in how many days?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?
A can do a work in 12 days, B can do it in 20 days and C in 15 days. If they work together the number of days needed to complete the work is: