If 30 workers can do a work in 40 days. In how many days will 40 workers do the same work?

A30 days

B25 days

C35 days

D20 days

Answer:

A. 30 days

Read Explanation:

time taken by 40 workers = (30x40)/ 40 = 30 days


Related Questions:

Abhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
12 ആളുകൾ 25 ദിവസംകൊണ്ട് ചെയ്തുതീർക്കുന്ന ജോലി 15 ദിവസംകൊണ്ട് തീർക്കാൻ ഇനി എത ആളുകൾ കൂടി വേണം?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?