In a computer game, a builder can build a wall in 20 hours while a destroyer can completely demolish such a wall in 40 hours. In the beginning, both builder and destroyer were set to work together on a basic level. But after 30 hours the destroyer was withdrawn. What was the total time taken to build the wall?

A33 h 30 min

B35 h

C35 h 15 min

D32 h 45 min

Answer:

B. 35 h

Read Explanation:

Solution: Given: A builder can build a wall in 20 hours while a destroyer can completely demolish such a wall in 40 hours. But after 30 hours the destroyer was withdrawn. Concept Used: Using the Least Common Multiple(LCM) Methods Calculation: Let the bulider can bulid the wall be P in 20 hours, and detsroyer demolish the wall be Q in 40 hours Total Work = LCM of (20 and 40) ⇒ 40 Effiiciency of P = 40/20 = 2 Efficiency of Q = 40/40 = 1 Both builder and destroyer were set to work together 30 h ⇒ 30 × (2 - 1) ⇒ 30 unit Remaining work = 40 - 30 = 10 unit After 30 h, destroyer was withdrawn, remainig work by P ⇒ 10/2 ⇒ 5 h Total time to complete the work ⇒ 30 + 5 = 35 h ∴ The total time taken to build the wall was 35 h.


Related Questions:

6/7 part of a tank is filled with oil. After taking out 60 litres of oil the tank is 4/5 part full. What is the capacity (in litres) of the tank?
A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?
20 ദിവസം കൊണ്ട് 15 പേർ കുളം കുഴിക്കുന്ന ജോലി ഏറ്റെടുത്തു. 10 ദിവസത്തിന് ശേഷം 5 പേർ വിട്ടുപോയി. വീണ്ടും 5 ദിവസത്തിന് ശേഷം 5 പേർ കൂടി പോയി. ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസം വേണ്ടിവരും?
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is: