App Logo

No.1 PSC Learning App

1M+ Downloads
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A$$13\frac23$ days$

B$$13\frac13$ days$

C$$14\frac23$ days$

D$$14\frac13$ days$

Answer:

$$13\frac23$ days$

Read Explanation:

raju =12 days

raman 16 days

total work is the LCM=48

efficiency(one day work) of raju =48/12=4

efficiency(one day work) of raman =48/16=3

alternate days work start with raju

4,3,4,3,4,3,....

for 13 days the work is 46 then the next work is raman

one day work of raju is 3 but the work left is 2 so the work is 2/3

so the total work days is 13 and 2/3 days


Related Questions:

4 ടാപ്പുകൾക്ക് 10 മണിക്കൂർ കൊണ്ട് ഒരു ടാങ്ക് നിറക്കാൻ കഴിയും. അപ്പോൾ 6 ടാപ്പുകൾക്ക് ഇതേ ടാങ്കിൽ എത്ര മണിക്കൂർ കൊണ്ട് നിറയ്ക്കാനാകും?
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
51 men can complete a work in 12 days. Four days after they started working 6 more men joined them. How many days will they now take to complete the remaining work?
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
10 ദിവസം കൊണ്ടാണ് A ഒരു ജോലി പൂർത്തിയാക്കുന്നത്. A 6 ദിവസം ജോലി ചെയ്തു. ശേഷം വിട്ടുപോകുന്നു. ശേഷിക്കുന്ന ജോലി B 2 ദിവസം കൊണ്ട് തീർക്കുന്നു. B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കും?