App Logo

No.1 PSC Learning App

1M+ Downloads

A can do 15\frac{1}{5}th of a work in 4 days and B can do 16\frac{1}{6}th of the same work in 5 days. In how many days they can finish the work, if they work together?

A12

B20

C15

D30

Answer:

A. 12

Read Explanation:

Solution;

A can do 15\frac{1}{5}th work in 4days.

Efficiency of A = 14×5=120\frac{1}{4\times5}=\frac{1}{20}

B can do 16\frac{1}{6}th of the work in 5days.

Efficiency of B = 16×5=130\frac{1}{6\times5}=\frac{1}{30}

Combined Efficiency of A and B is = 120+130\frac{1}{20}+\frac{1}{30}

=3+260=560=112=\frac{3+2}{60}=\frac{5}{60}=\frac{1}{12}

A and B together can complete the work in 12 days.

Shortcut:

image.png

A can do 1/5th of a work in = 4 days

A can do the whole work in = 4×5=20days4\times 5 = 20 days

B can do 1/6th of the same work in = 5 days

B can do the whole work in = 5×6=30days5 \times 6 = 30 days

From the following figure

Total work = 60

Total efficiency of A and B = 2 + 3 = 5

A and B together can complete the whole work in = 605=12days\frac{60}{5} = 12 days


Related Questions:

Two pipes A and B can fill a tank in 6 hours and 9 hours respectively. They are opened alternately for 1 hour each starting with pipe A first. In how many hours the tank will be filled?
Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24 days joined them after 4 days. Under the circumstances in how many days the work will be completed?
Pointing to a boy, Remya said "He is the son of my grandmoth- er's only child." How is the boy related to Remya?
Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men take in 20 days to complete the job?
A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?