Challenger App

No.1 PSC Learning App

1M+ Downloads
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?

A48

B36

C60

D72

Answer:

C. 60

Read Explanation:

Required number of days = (30 * 36)/18= 60


Related Questions:

A pipe can fill an empty tank in 15 hours, but due to a leakage at the bottom, it is filled in 20 hours. If the tank is full, how long will the leakage take to empty it if no other entry or exit point in the tank is open?
Suresh can complete a job in 15 hours. Ashutosh alone can complete the same job in 10 hours. If Suresh works alone for 9 hours and then stops, how many hours will it take Ashutosh to complete the job alone?
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank ifthe capacity of each bucket is 9 litres?
Amit can complete a piece of work in 120 days. Amit and Sejal can complete the same work in 72 days. They started together but Sejal left after working for 20 days. Find the approximate number of days in which Amit will complete the remaining work.