Challenger App

No.1 PSC Learning App

1M+ Downloads
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?

A48

B36

C60

D72

Answer:

C. 60

Read Explanation:

Required number of days = (30 * 36)/18= 60


Related Questions:

A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
There are two pipes in a tank if pipe A is opened the tank will be filled in 10 minutes and if pipe B is opened it will be filled in 15 minutes. If both are open together in how many minutes will it be filled ?
Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
Sita is twice efficient than Gita. If together they complete the work in 15 days. Find the difference of number of days between Gita and Sita.
Ramanan and Shyam together can do a work in 8 days. Both of B them began to work. After 3 days Ramanan fell ill, Shyam completed the remaining work in 15 days. In how many days can Ramanan complete the work?