App Logo

No.1 PSC Learning App

1M+ Downloads
X, Y and Z can complete a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 7 days. If Z joined them after 8 days from the beginning, then for how many days did Y work?

A125712\frac{5}{7}

B115711\frac{5}{7}

C105710\frac{5}{7}

D9579\frac{5}{7}

Answer:

115711\frac{5}{7}

Read Explanation:

Solution:

Given data:

Days in which X can complete the work = 46 days

Days in which Y can complete the work = 92 days

Days in which Z can complete the work = 23 days

Days after which Y joined = 7 days

Days after which Z joined = 8 days

Formula used:

Efficiency = Total work / Time taken to complete work individually

Calculation:

LCM of 23, 46, 92 = 92

Assuming that the total work is 92 units.

Efficiency of x-

9246=2\frac{92}{46}=2units of work/day

Efficiency of y-

9292=1\frac{92}{92}=1


Efficiency of z-

9223=4\frac{92}{23}=4

Work done in 7 days by X working alone = 2 units × 7 = 14 units

Work done by X and Y on 8th day =  (2 + 1) × 1 = 3 units

Total work done until 8th day = 14 + 3 = 17 units

Remaining work = 92 - 17 = 75 units

Work done by X , Y and Z in one day = 2 + 1 + 4 = 7 units

Total time taken =757days=\frac{75}{7}days

Total days worked by Y =757+1=827=1157days=\frac{75}{7}+1=\frac{82}{7}=11\frac{5}{7}days


Related Questions:

If 16 men or 20 women can do a piece of work in 25 days. In what time will 28 men and 15 women do it?
18 പേർ 28 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 24 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ എത ജോലിക്കാർ വേണം?
The efficiency of A, B, and C is 2 : 3 : 5. A alone can complete a work in 50 days. They all work together for 5 days and then C left the work, in how many days A and B together can complete the remaining work?
Two pipes can fill a cistern separately in 10 hours and 15 hours. They can together fill the cistern in
30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?